O

Oracle Project Portfolio Management Cloud 2018 Implementation Essentials

76 Questions

You can start the exam to practice all questions related to this exam.

Question No. 1

Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions?
 

Choose the correct option from the given list.