G
GIAC Certified Project Manager
340 Questions
Question No. 1
Which of the following is described in the statement below?
"It measures the quality objectives of the project. It provides the foundation for measuring and reporting quality performance as part of the performance measurement baseline."
Choose the correct option from the given list.
01 / 340