Question No. 1
Which is a purpose of the Controlling a Stage process?
Choose the correct option from the given list.
Assign work to be done and take corrective action to ensure that the stage remains within tolerance
Provide a fixed reference point at which acceptance for the project product is confirmed
Enable the Project Board to be provided with sufficient information to authorize the next stage
Enable the organization to understand the work that needs to be done to deliver the project's products
Reveal Answer
01 / 312