P

Project Management Professional

2131 Questions

You can start the exam to practice all questions related to this exam.

Question No. 1

The project management team has performed earned value analysis on its project and discovered that the project is behind schedule and over budget. The SPI is 0.82 and the CPI is 0.73. The team is trying to determine how efficient it will need to be with the remaining resources on the project to complete the project on budget. Which of the following is the team trying to calculate? 

Choose the correct option from the given list.
01 / 2131

0 Discussions

Trending Exams