I
ISTQB Certified Tester Foundation Level
339 Questions
Question No. 1
Refer to the exhibit, The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window
The first activity is to run any re-tests, followed by the regression test script. Users have supplied their priority order to tests. Which of the following gives an appropriate test execution schedule, taking account of the prioritization and other constraints?
Choose the correct option from the given list.
01 / 339