Question No. 1
Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project. What scheduling technique is Kelly using?
Choose the correct option from the given list.