P
PMI Scheduling Professional
302 Questions
Question No. 1
John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress.
Which of the following techniques is used in generating performance reports?
Choose the correct option from the given list.
01 / 302