Question No. 1

During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes it is not possible to meet it. The project manager meets with all parties concerned to analyze the situation. 

Which part of the quality management process is the project manager involved in?

Choose the correct option from the given list.