G

GIAC Certified Project Manager

340 Questions

You can start the exam to practice all questions related to this exam.

Question No. 1

Alan works as a project manager for HRM Inc. He is working on the office renovation project. The office has 200 doors. All doors have to be glassed and painted. Before each door can be painted, the glasses must be fitted in them at least 12 hours before. Alan has arranged these tasks with a finish to start relationship between glassing and painting. What else should Alan do to account for the twelve hours of maintenance time? 

Choose the correct option from the given list.
01 / 340

0 Discussions

Trending Exams