Question No. 1

A project manager developed a project management plan for a team composed of members based in three countries. The project manager assumed a 40-hour work week for all team members. However, during project execution, the project manager learns that one country’s team members work a 35-hour week. Where should this information have been captured? 

Choose the correct option from the given list.